Nam Ngum 3 Hydropower Plant to Begin Power Generation in Early 2027

06/01/2025 14:42
Email Print 5022
ຂປລ The Nam Ngum 3 Hydropower Plant project is currently over 80% complete and is expected to be operational and begin generating electricity in early 2027. Once finished, it will be the tallest rockfill dam in ASEAN at 210 meters.

(KPL) The Nam Ngum 3 Hydropower Plant project is currently over 80% complete and is expected to be operational and begin generating electricity in early 2027. Once finished, it will be the tallest rockfill dam in ASEAN at 210 meters.
Mr. Phoukham Sithidala, Head of the Nam Ngum 3 Hydropower Plant Construction Project, recently stated that the project spans three districts across two provinces – Phoukoud district in Xieng Khuang Province, and Anouvong and Long Cheng districts in Xaysomboun Province. 
Construction began in 2013, with initial plans to complete the project and commence power generation in 2021. However, financial challenges caused delays, temporarily halting the project. 
Construction resumed late last year.
The Nam Ngum 3 Hydropower Plant will have a total installed generation capacity of 480 MW and is projected to generate 2,345 GWh of electricity per year. The project aims to enhance the country’s energy stability by supplying electricity for domestic consumption.

 
KPL

ຂ່າວອື່ນໆ

    • Laos Signs MOU for Solar Energy Project in Two ProvincesEconomics

      Laos Signs MOU for Solar Energy Project in Two Provinces

      3/28/2025 2:52:58 PM

      The government signed a Memorandum of Understanding (MOU) with AB Construction and Shaochun Hung Heuang Co., Ltd. to conduct a feasibility study for a solar power project in Bolikhamxay and Sekong provinces on March 26, 2025.

    • Laos Energy Development Plan for Net-Zero Emissions UnveiledEconomics

      Laos Energy Development Plan for Net-Zero Emissions Unveiled

      3/26/2025 12:16:21 PM

      The ASEAN Centre for Energy (ACE) has released a study titled "Energy Sector Development Plan for Net-Zero Emissions in Laos". The study, published on March 25, 2025, underscores Laos’ commitment to achieving net-zero greenhouse gas emissions by 2050, aligning with its Nationally Determined Contributions (NDC) under the Paris Agreement.

    • Vietnam, Laos promote payments in local currencies to boost trade Economics

      Vietnam, Laos promote payments in local currencies to boost trade

      3/17/2025 9:39:17 AM

      (KPL/VNA) A conference was held in Vientiane on March 14 to promote the use of the Lao kip (LAK) and the Vietnam dong (VND) in payments for goods and services between the two countries.

    • Laos, China Launch 500-kV Interconnection ProjectEconomics

      Laos, China Launch 500-kV Interconnection Project

      2/27/2025 2:05:53 PM

      The Laos-China 500-kV Interconnection Project, a key initiative under the China-Laos Community with a Shared Future Action Plan, is set to be completed and operational by 2026.

    • Vietnam, Laos strengthen energy cooperationEconomics

      Vietnam, Laos strengthen energy cooperation

      2/17/2025 11:32:52 AM

      (KPL/VNA) The Lao Government and Chitchareune Construction Co., Ltd. on February 13 signed an agreement to develop a 1,200 MW wind power plant in Nong district, Laos’ Savannakhet province which aims to supply electricity to Vietnam from late 2027.