The Lao Government is stepping up preparations for the construction of a 490-kilometre strategic road along the Laos-Vietnam border, with officials meeting in Khammouane Province on November 19, 2026, to coordinate responsibilities and accelerate project implementation.

(KPL) The road, known as the Laos-Vietnam Friendship Road, is intended to strengthen national defence and public security infrastructure while improving connectivity in border areas.
The meeting was chaired by Lt. Gen. Saichay Kommasith, Deputy Minister of National Defense and Chief of the General Staff of the Lao People's Army. It was attended by Mr. Manyeun Khinsamone, Vice Chairman of the Khammouane Provincial Administration Committee, and representatives of relevant government agencies and sectors.
During the meeting, Brig. Gen. Ophath Thammathong, Head of the Office of the General Staff of the Ministry of National Defense, presented Agreement No. 44/ND-PS on the appointment of the project's steering committee and working group.
The agreement defines the roles and responsibilities of the committees and establishes coordination arrangements to ensure that construction proceeds according to schedule and complies with relevant laws and regulations.
The project is also intended to support the development of a wind power project by CLE 1 Co., Ltd. and strengthen the strategic road network along the border. Funding will be provided through assistance from the Vietnamese Government, with CLE 1 Co., Ltd. responsible for financing the project.
The planned 490-kilometre route will cross three provinces: Khammouane, Bolikhamxay and Xiengkhouang. It will begin at Ban Phone in Boualapha District, Khammouane Province, pass through Ban Maka and Namphao in Bolikhamxay Province, and extend to Ban Nam On and Ban Nam Kan in Xiengkhouang Province.
Construction will be carried out in three phases:
Phase 1: Ban Phone–Ban Maka, covering 92 kilometres.
Phase 2: Ban Maka–Namphao, covering 140 kilometres.
Phase 3: Namphao–Ban Nam On–Ban Nam Kan, covering 258 kilometres.
Lt. Gen. Saichay Kommasith instructed the responsible committees and relevant agencies to clearly understand their duties, inspect the proposed road alignment and develop detailed implementation plans.
He also stressed the need for close coordination to identify forest areas that could be affected by construction, monitor project progress and promptly address any challenges that arise.
The meeting also heard a report from the Nakai-Nam Theun National Park Office on the park's boundaries and potential impacts from the proposed route. Participants discussed measures to address these issues and ensure that project implementation follows approved plans and relevant regulations.
Once completed, the road is expected to improve connectivity across border areas in the three provinces while supporting infrastructure development, national defence and public security cooperation between Laos and Vietnam.