Laos Launches Major Phase of Vientiane–Hanoi Expressway Project

05/12/2025 09:51
Email Print 1471
KPL Construction of Section 2 of the Vientiane–Hanoi Expressway is now under way, following the signing of the project contract in mid-October. By the end of October 2025, the developer, Namtha Construction-Bridge-Road Sole Co., Ltd., had already mobilised machinery and technical teams to begin work.

(KPL) Construction of Section 2 of the Vientiane–Hanoi Expressway is now under way, following the signing of the project contract in mid-October. By the end of October 2025, the developer, Namtha Construction-Bridge-Road Sole Co., Ltd., had already mobilised machinery and technical teams to begin work.

The 203.8-kilometre section runs from Paksan district to the Laos–Vietnam border in Xaychamphon district, Bolikhamxay province.

Mr Lienthong Vonghachack, Deputy Head of the Vientiane–Hanoi Expressway Construction Project (Sections 1 and 2), said the developer is pressing ahead with the first phase of implementation, setting up multiple work fronts along the route. The project is scheduled for completion within four years, by 2029.

According to Mr Lienthong, three categories of work will proceed in parallel:

Earthworks and structural works along every 10–20 km of the route

Bridge construction at all river crossings

Concrete paving in flat areas where earthworks have been finished

Construction will run around the clock, with additional foreign labour brought in to ensure progress meets the project timeline.

Section 2 is considered a key component in Laos’ broader connectivity strategy. Located between Vietnam and Thailand, the country sits along an emerging global trade corridor linking India, Europe and ASEAN with China, the Republic of Korea and Japan.

Currently, most cargo between these regions moves by sea through Singapore, a route used by around 100,000 vessels each year with a combined cargo value estimated at USD 1 trillion. Once operational, the expressway is expected to shift a portion of this traffic to overland transport. The land route from Thailand’s Ranong Port to Hong Kong is roughly 3,000 km—about 1,000 km shorter than the equivalent sea route via Singapore—offering significant time and safety advantages.

Thailand and Vietnam have already completed railway and expressway links up to the Lao border, pending the finalisation of this expressway section.

Laos is expected to gain substantial benefits upon completion, including:

Economic gains, with projected revenue of more than USD 1 billion annually through increased investment, tourism and service-sector expansion

Enhanced security and strategic relevance, strengthening the country’s role in regional and international transport networks.

KPL

ຂ່າວອື່ນໆ

    • Chinese Consulate General in Luang Prabang Celebrates International Women’s DayGeneral

      Chinese Consulate General in Luang Prabang Celebrates International Women’s Day

      3/10/2026 5:42:55 PM

      The Consulate General of the People’s Republic of China in Luang Prabang held a ceremony on March 6 to celebrate the 116th anniversary of International Women’s Day, while also marking the upcoming 65th anniversary of diplomatic relations between China and Laos, officially established on April 25.

    • WFP Project Boosts Rural Livelihoods and School Nutrition in OudomxayGeneral

      WFP Project Boosts Rural Livelihoods and School Nutrition in Oudomxay

      3/10/2026 4:48:53 PM

      A community-based agriculture initiative supported by the World Food Programme (WFP) is helping rural families in northern Laos improve their livelihoods while strengthening food supplies for school meal programmes.

    • Japan-Funded Irrigation and Road Project Boosts Rural Livelihoods in Northern LaosGeneral

      Japan-Funded Irrigation and Road Project Boosts Rural Livelihoods in Northern Laos

      3/10/2026 3:21:06 PM

      Ambassador of Japan to the Lao PDR, the FAO Representative, and the Director General of the Ministry of Agriculture and Environment (MAE) conducted a joint high-level field mission to project sites as the Food and Agriculture Organization of the United Nations (FAO) and the Japan completed 31 irrigation systems and 17 road infrastructure projects across Luang Prabang Province and Oudomxay Province under the Livelihood Resilience in Rural Areas (LRRA) Project, directly benefiting more than 1,200 farming households.

    • PSC Delegation Extends International Women’s Day Greetings to NA Vice PresidentGeneral

      PSC Delegation Extends International Women’s Day Greetings to NA Vice President

      3/10/2026 3:14:05 PM

      On the occasion of the 116th anniversary of International Women’s Day (March 8, 1910 – March 8, 2026), Dr. Anong Gnoysaikham, Vice President of the People’s Supreme Court of Laos, led a delegation to extend congratulations and best wishes to Dr. Sounthone Xayachack, Vice President of the National Assembly of Laos.

    • Free BRT Bus Service Launched in Vientiane for Two-Month TrialGeneral

      Free BRT Bus Service Launched in Vientiane for Two-Month Trial

      3/10/2026 11:05:31 AM

      An official ceremony was held on March 10, 2026, in Vientiane to launch the Bus Rapid Transit (BRT) system, with free service offered from March 10 to May 9, 2026 as part of a trial operation.


Top