Vietnam accelerates transmission projects to support power imports from Laos

08/10/2025 11:12
KPL (KPL/VNA) The National Power Transmission Corporation (EVNNPT) is accelerating two key 220 kV transmission line projects - Tuong Duong–Do Luong and Do Luong–Nam Cam - to strengthen power supply in Nghe An province and enable electricity imports from Laos, with completion targeted for November.

(KPL/VNA) The National Power Transmission Corporation (EVNNPT) is accelerating two key 220 kV transmission line projects - Tuong Duong–Do Luong and Do Luong–Nam Cam - to strengthen power supply in Nghe An province and enable electricity imports from Laos, with completion targeted for November.

The Tuong Duong – Do Luong line spans over 80 km with two 220 kV circuits linking the Tuong Duong and Do Luong substations. In Nghe An province, all 192 tower foundations have been handed over, with 44 of 58 corridor segments cleared. Construction has completed 182 out of 192 towers and nearly 33 km of wiring.

The 37 km Do Luong – Nam Cam line, also with two circuits, has cleared 105 of 106 foundations and 38 of 51 segments. So far, 87 foundations, 83 towers and over 13 km of wiring have been completed, with work ongoing at several sites.

According to the Central Vietnam Power Projects Management Board (CPMB), the projects are broadly on schedule. But adverse weather, particularly storms between September and early October, has caused delays, especially in mountainous or flood-prone zones where access roads were damaged or sites submerged. Some localities have also yet to hand over all required land and corridor.

CPMB continues coordinating with land compensation committees and local authorities to meet with affected households, explain project policies, and encourage timely land handover.

At a review meeting on October 6, EVNNPT Deputy General Director Truong Huu Thanh commended the large volume of completed work, but stressed that overall progress still falls short of expectations.

The projects aims to transmit electricity from Lao wind farms, the Nam Mo hydropower cluster, and small and medium plants in western Nghe An to the national grid, enhancing supply reliability, strengthening regional grid connectivity, and supporting Nghe An’s industrial growth and socio-economic development.

Thanh urged CPMB and local authorities in Nghe An to promptly resolve land clearance issues and accelerate construction.

He requested contractors to add manpower, carry out foundation excavation, tower erection, and wiring simultaneously, and continue coordinating with CPMB to facilitate the handover of foundation locations for construction; while maintaining close coordination to ensure project completion by early November 2025 as directed by EVN.

 

 

 

 

 

KPL

ຂ່າວອື່ນໆ

    • Online Licensing System for Digital Technology Work Officially LaunchedGeneral

      Online Licensing System for Digital Technology Work Officially Launched

      10/8/2025 11:17:20 AM

      The launch ceremony for the Online Licensing System Database for Digital Technology Work took place on October 6, 2025, at the Lao Digital Park in Vientiane.

    • National Blood Institute Reviews Mid-Year Donation Drive, Aims to Boost Voluntary DonationsGeneral

      National Blood Institute Reviews Mid-Year Donation Drive, Aims to Boost Voluntary Donations

      10/7/2025 8:23:07 PM

      The National Blood Transfusion Institute (NBTI) of the Lao Red Cross convened a meeting on October 6 to review its public blood donation campaign for the first half of 2025 and to outline its strategy for the remainder of the year.

    • Laos Celebrates 31st National Teacher’s DayGeneral

      Laos Celebrates 31st National Teacher’s Day

      10/7/2025 6:28:46 PM

      On October 6, schools across the country held ceremonies to celebrate the 31st anniversary of Lao National Teacher’s Day (Oct 7, 1994 - 2025). The celebrations featured a variety of joyous activities, including lectures, poetry readings honoring teachers, student art performances, and the traditional teacher homage (wai ku).

    • Tavanh Sengdala Wins First Laos Young Barista Championship 2025General

      Tavanh Sengdala Wins First Laos Young Barista Championship 2025

      10/7/2025 3:46:04 PM

      In a thrilling showcase of talent and passion, Mr. Tavanh Sengdala emerged as the winner of the first-ever Laos Young Barista Championship 2025, held during the International Coffee and Tea Day (ICTD) celebrations. His exceptional performance earned him not only the top prize of 5 million LAK, but also the honor of representing Laos at the World Barista Championship in Korea this November.

    • Luang Prabang Brews Success at International Coffee and Tea Day 2025General

      Luang Prabang Brews Success at International Coffee and Tea Day 2025

      10/7/2025 2:45:52 PM

      More than 6,400 people gathered in Luang Prabang from 3 to 5 October to celebrate the International Coffee and Tea Day (ICTD) 2025, transforming the UNESCO World Heritage City into a dynamic hub for farmers, entrepreneurs, roasters, traders, and development partners. The event showcased Lao coffee and tea as key drivers of sustainable growth and agricultural development.


Top